Tuesday, 20 February 2024
Monday, 19 February 2024
Filleted bow compartment, planed flush deck joint,
filled screw holes
Today I finished up the fillet under the deck in bow compartment - I had to take a break from the monstrous overhead fillet job the previous day. I am in two minds to leave it as it is or to add a layer of glass - it can always wait as I made sure to leave good access.
then I planed the deck joint down, companionway bulkhead and also the cockpit coamings, and filled some screw holes in preparation for the round over of the sharp corners
- all for the glassing work to come, there are plenty more screws to fill !!!!
then I planed the deck joint down, companionway bulkhead and also the cockpit coamings, and filled some screw holes in preparation for the round over of the sharp corners
- all for the glassing work to come, there are plenty more screws to fill !!!!
Subscribe to:
Posts (Atom)
A round the world non stop record challenge in a modified 5.8m Class Globe Alessio Campriani is busy with his challenge at the smallest bo...
-
Chainplates complete The chainplates were the most complicated of the stainless items, the rest will progress quicker as they are way simpl...
-
The forepeak/cargo hold door has been fitted This is the door to the front of the boat that will create a watertight closure at the mast b...
-
Where it all began and why I decided on a a SETKA A 5m over a Class Globe 580 In March 2020 - I saw on the internet what I thought was a ...