Saturday, 25 February 2023

 Frame A is completed 


Today all the gussets were cut out and the frame was epoxy glued together and then the plywood gussets were epoxy glued and screwed onto the frame.



Frame A started C completed

 Today frame A parts were cut to size and gusset templates made. Frame C completed.



Thursday, 23 February 2023

 Frame C gussets cut and in progress


Frame C had its 60mm frame cut from a plank and fitted. Plywood was removed from the stack and templates for the gussets for the frame were measured from the plans and were cut from the plywood and epoxy glued and screwed to the bulkhead frame, 








and the infill for the deck beam was epoxied on 




and the final gussets will be glued and screwed on after the temporary screws holding the frame to the lofting board are removed. 


 NMEA connections and the low power interior lights Just some futher pictures from the last few weeks all the NMEA connections are contained...