Thursday, 23 February 2023

 Frame C gussets cut and in progress


Frame C had its 60mm frame cut from a plank and fitted. Plywood was removed from the stack and templates for the gussets for the frame were measured from the plans and were cut from the plywood and epoxy glued and screwed to the bulkhead frame, 








and the infill for the deck beam was epoxied on 




and the final gussets will be glued and screwed on after the temporary screws holding the frame to the lofting board are removed. 


No comments:

Post a Comment

  The forepeak/cargo hold door has been fitted This is the door to the front of the boat that will create a watertight closure at the mast b...